Case Study · NOIDA BESS
Replacing Diesel in High-Rise Towers, NOIDA
High-density residential and commercial towers needing 2 to 5 MW face severe outages and strict anti-diesel mandates.


Challenge
- Burning 15 to 20 litres of diesel per hour
- OPEX of INR 18 to 20 per kWh
- Local PM2.5 above 150 μg/m³, violating CAQM directives
Solution
- Custom LiFePO4 BESS, 500 kWh to 2.4 MWh per tower
- Integrated with existing solar (or standalone)
- Legacy DG retained only as tier-2 fail-safe

Outcomes
From ~INR 20/kWh on diesel to INR 2 to 3/kWh on BESS
85–90%
cost savings: from ~INR 20/kWh (diesel) to INR 2 to 3/kWh (BESS)
80%
up to 80% cut in peak-hour energy charges
15–20t
tonnes CO₂ eliminated per MW per year (potential)
4–5yrs
payback

Stop burning capital on diesel and peak tariffs.
Our energy architects model your exact load profile, hour by hour, and show you projected OPEX savings, peak-shaving impact, solar gains and payback timeline down to the month.